Portfolio Analysis Report
IACC Autism Spectrum Disorder Research
2009
Appendix A: ASD Research Progress on 2010 IACC Strategic Plan Objectives
Data includes 2009 funding from Federal/private funders of ASD research and 2009 NIH-ARRA funding. |
|
Current project and funding status for each question or objective is indicated within the table by colored "dots" next to the objective. Any objective colored green has greater than or equal to the recommended funding; any objective colored yellow has some degree of funding, but less than the recommended amount; while any objective colored red has no funding. |
|
New! |
Objectives labeled "New!" are either entirely new additions to the 2010 Strategic Plan or significantly modified objectives from the 2009 Strategic Plan. Objectives from the 2009 Strategic Plan that did not change or that have been slightly modified for clarification purposes in the 2010 Strategic Plan are unmarked. |
The percentages noted in parentheses in the "Projects" and "Funding" columns indicate the fraction of all projects or funding within that specific question, whereas the percentage in the "Percent of Total ASD Funding" column indicates the percent of the entire ASD research funding portfolio for 2009.
Question 1: When should I be concerned?
2010 IACC Strategic Plan Objectives | Projects | Funding | Percent of Total ASD Funding |
---|---|---|---|
2010 IACC Strategic Plan Objectives 1.S.A | Projects15 |
FundingD$4,728,120 |
Percent of Total ASD Funding2% |
2010 IACC Strategic Plan Objectives 1.S.B | Projects11 |
Funding$3,973,711 |
Percent of Total ASD Funding1% |
2010 IACC Strategic Plan ObjectivesNew! | Projects1 |
Funding$139,072 |
Percent of Total ASD Funding<1% |
2010 IACC Strategic Plan ObjectivesNew! | Projects0 |
Funding$0 |
Percent of Total ASD Funding0% |
2010 IACC Strategic Plan Objectives 1.L.A | Projects43 |
Funding$16,465,034 (37%) |
Percent of Total ASD Funding5% |
2010 IACC Strategic Plan Objectives 1.L.B | Projects34 |
Funding$8,760,010 |
Percent of Total ASD Funding3% |
2010 IACC Strategic Plan Objectives 1.L.C | Projects6 |
Funding$861,069 |
Percent of Total ASD Funding<1% |
2010 IACC Strategic Plan Objectives1.O Not specific to any objective | Projects37 |
Funding$9,766,926 |
Percent of Total ASD Funding3% |
Total Funding for Question 1 | Projects147 |
Funding$44,693,942 |
Percent of Total ASD Funding14% |
The percentages noted in parentheses in the "Projects" and "Funding" columns indicate the fraction of all projects or funding within that specific question, whereas the percentage in the "Percent of Total ASD Funding" column indicates the percent of the entire ASD research funding portfolio for 2009.
Question 2: How can I understand what is happening?
2010 IACC Strategic Plan Objectives | Projects | Funding | Percent of Total ASD Funding |
---|---|---|---|
2010 IACC Strategic Plan Objectives 2.S.A | Projects30 |
Funding$3,584,634 |
Percent of Total ASD Funding1% |
2010 IACC Strategic Plan Objectives 2.S.B | Projects5 |
Funding$1,370,107 |
Percent of Total ASD Funding<1% |
2010 IACC Strategic Plan Objectives 2.S.C | Projects2 |
Funding$726,911 |
Percent of Total ASD Funding<1% |
2010 IACC Strategic Plan ObjectivesNew!
| Projects48 |
Funding$9,171,542 |
Percent of Total ASD Funding3% |
2010 IACC Strategic Plan ObjectivesNew!
| Projects11 |
Funding$3,893,300 |
Percent of Total ASD Funding1% |
2010 IACC Strategic Plan ObjectivesNew!
|
Projects0 |
Funding$0 |
Percent of Total ASD Funding0% |
2010 IACC Strategic Plan ObjectivesNew! | Projects21 |
Funding$5,903,875 |
Percent of Total ASD Funding2% |
2010 IACC Strategic Plan Objectives 2.L.A | Projects6 |
Funding$2,721,384 |
Percent of Total ASD Funding1% |
2010 IACC Strategic Plan ObjectivesNew! | Projects16 |
Funding$1,532,262 |
Percent of Total ASD Funding<1% |
2010 IACC Strategic Plan Objectives | Projects163 |
Funding$34,348,932 (54%) |
Percent of Total ASD Funding11% |
2010 IACC Strategic Plan ObjectivesTotal Funding for Question 2 | Projects302 |
Funding$63,252,949 |
Percent of Total ASD Funding20% |
The percentages noted in parentheses in the "Projects" and "Funding" columns indicate the fraction of all projects or funding within that specific question, whereas the percentage in the "Percent of Total ASD Funding" column indicates the percent of the entire ASD research funding portfolio for 2009.
Question 3: What caused this to happen and can it be prevented?
2010 IACC Strategic Plan Objectives | Projects | Funding | Percent of Total ASD Funding |
---|---|---|---|
2010 IACC Strategic Plan Objectives 3.S.A | Projects11 |
Funding$13,926,663 |
Percent of Total ASD Funding4% |
2010 IACC Strategic Plan Objectives 3.S.B | Projects0 |
Funding$0 |
Percent of Total ASD Funding0% |
2010 IACC Strategic Plan Objectives 3.S.C | Projects9 |
Funding$8,033,454 |
Percent of Total ASD Funding3% |
2010 IACC Strategic Plan Objectives 3.S.D | Projects3 |
Funding$103,827 |
Percent of Total ASD Funding<1% |
2010 IACC Strategic Plan ObjectivesNew! | Projects13 |
Funding$1,739,200 |
Percent of Total ASD Funding1% |
2010 IACC Strategic Plan ObjectivesNew! | Projects14 |
Funding$2,952,960 |
Percent of Total ASD Funding1% |
2010 IACC Strategic Plan Objectives 3.L.A | Projects2 |
Funding$3,740,812 |
Percent of Total ASD Funding1% |
2010 IACC Strategic Plan Objectives 3.L.B | Projects79 |
Funding$49,905,587 |
Percent of Total ASD Funding16% |
2010 IACC Strategic Plan Objectives 3.L.C | Projects10 |
Funding$1,992,228 |
Percent of Total ASD Funding1% |
2010 IACC Strategic Plan Objectives 3.L.D | Projects12 |
Funding$9,135,505 |
Percent of Total ASD Funding3% |
2010 IACC Strategic Plan Objectives | Projects39 |
Funding$8,512,980 |
Percent of Total ASD Funding3% |
2010 IACC Strategic Plan ObjectivesTotal Funding for Question 3 | Projects192 |
Funding$100,043,216 |
Percent of Total ASD Funding32% |
The percentages noted in parentheses in the "Projects" and "Funding" columns indicate the fraction of all projects or funding within that specific question, whereas the percentage in the "Percent of Total ASD Funding" column indicates the percent of the entire ASD research funding portfolio for 2009.
Question 4: Which treatments and interventions will help?
2010 IACC Strategic Plan Objectives | Projects | Funding | Percent of Total ASD Funding |
---|---|---|---|
2010 IACC Strategic Plan Objectives 4.S.A | Projects6 |
Funding$4,733,841 |
Percent of Total ASD Funding2% |
2010 IACC Strategic Plan Objectives 4.S.B | Projects70 |
Funding$20,162,709 |
Percent of Total ASD Funding6% |
2010 IACC Strategic Plan Objectives 4.S.C | Projects29 |
Funding$3,252,941 |
Percent of Total ASD Funding1% |
2010 IACC Strategic Plan Objectives 4.S.D | Projects9 |
Funding$7,540,613 |
Percent of Total ASD Funding2% |
2010 IACC Strategic Plan ObjectivesNew! | Projects0 |
Funding$0 |
Percent of Total ASD Funding0% |
2010 IACC Strategic Plan ObjectivesNew!
| Projects42 |
Funding$9,791,270 |
Percent of Total ASD Funding3% |
2010 IACC Strategic Plan Objectives 4.L.A | 1110 |
Funding$1,168,146 |
Percent of Total ASD Funding<1% |
2010 IACC Strategic Plan Objectives 4.L.B | Projects2 |
Funding$132,263 |
Percent of Total ASD Funding<1% |
2010 IACC Strategic Plan ObjectivesNew! | Projects7 |
Funding$1,061,222 |
Percent of Total ASD Funding<1% |
2010 IACC Strategic Plan Objectives | Projects59 |
Funding$15,560,011 (25%) |
Percent of Total ASD Funding5% |
2010 IACC Strategic Plan ObjectivesTotal Funding for Question 4 | Projects234 |
Funding$63,403,014 |
Percent of Total ASD Funding20% |
The percentages noted in parentheses in the "Projects" and "Funding" columns indicate the fraction of all projects or funding within that specific question, whereas the percentage in the "Percent of Total ASD Funding" column indicates the percent of the entire ASD research funding portfolio for 2009.
Question 5: Where can I turn for services?
2010 IACC Strategic Plan Objectives | Projects | Funding | Percent of Total ASD Funding |
---|---|---|---|
2010 IACC Strategic Plan Objectives 5.S.A | Projects1 |
Funding$499,999 |
Percent of Total ASD Funding<1% |
2010 IACC Strategic Plan ObjectivesNew! | Projects6 |
Funding$446,340 |
Percent of Total ASD Funding<1% |
2010 IACC Strategic Plan ObjectivesNew! | Projects0 |
Funding$0 |
Percent of Total ASD Funding0% |
2010 IACC Strategic Plan Objectives 5.L.A | Projects10 |
Funding$5,460,809 |
Percent of Total ASD Funding2% |
2010 IACC Strategic Plan Objectives 5.L.B | Projects5 |
Funding$103,722 |
Percent of Total ASD Funding<1% |
2010 IACC Strategic Plan ObjectivesNew! | Projects6 |
Funding$132,494 |
Percent of Total ASD Funding<1% |
2010 IACC Strategic Plan Objectives | Projects8 |
Funding$2,004,687 |
Percent of Total ASD Funding1% |
2010 IACC Strategic Plan ObjectivesTotal Funding for Question 5 | Projects36 |
Funding$8,648,050 |
Percent of Total ASD Funding3% |
The percentages noted in parentheses in the "Projects" and "Funding" columns indicate the fraction of all projects or funding within that specific question, whereas the percentage in the "Percent of Total ASD Funding" column indicates the percent of the entire ASD research funding portfolio for 2009.
Question 6: What does the future hold, particularly for adults?
2010 IACC Strategic Plan Objectives | Projects | Funding | Percent of Total ASD Funding |
---|---|---|---|
2010 IACC Strategic Plan ObjectivesNew! | Projects1 |
Funding$20,000 |
Percent of Total ASD Funding<1% |
2010 IACC Strategic Plan ObjectivesNew! | Projects0 |
Funding$0 |
Percent of Total ASD Funding0% |
2010 IACC Strategic Plan ObjectivesNew! | Projects0 |
Funding$0 |
Percent of Total ASD Funding0% |
2010 IACC Strategic Plan ObjectivesNew! | Projects0 |
Funding$0 |
Percent of Total ASD Funding0% |
2010 IACC Strategic Plan ObjectivesNew! | Projects2 |
Funding$509,965 |
Percent of Total ASD Funding<1% |
2010 IACC Strategic Plan ObjectivesNew! | Projects2 |
Funding$718,290 |
Percent of Total ASD Funding<1% |
2010 IACC Strategic Plan ObjectivesNew! | Projects0 |
Funding$0 |
Percent of Total ASD Funding0% |
2010 IACC Strategic Plan ObjectivesNew! | Projects0 |
Funding$0 |
Percent of Total ASD Funding0% |
2010 IACC Strategic Plan Objectives | Projects2 |
Funding$159,444 |
Percent of Total ASD Funding<1% |
2010 IACC Strategic Plan ObjectivesTotal Funding for Question 6 | Projects7 |
Funding$1,407,699 |
Percent of Total ASD Funding<1% |
The percentages noted in parentheses in the "Projects" and "Funding" columns indicate the fraction of all projects or funding within that specific question, whereas the percentage in the "Percent of Total ASD Funding" column indicates the percent of the entire ASD research funding portfolio for 2009.
Question 7: What other infrastructure and surveillance needs must be met?
2010 IACC Strategic Plan Objectives | Projects | Funding | Percent of Total ASD Funding |
---|---|---|---|
2010 IACC Strategic Plan Objectives 7.A | Projects0 |
Funding$0 |
Percent of Total ASD Funding0% |
2010 IACC Strategic Plan Objectives 7.B | Projects1 |
Funding$7,061 |
Percent of Total ASD Funding<1% |
2010 IACC Strategic Plan Objectives 7.C | Projects2 |
Funding$1,665,180 |
Percent of Total ASD Funding1% |
2010 IACC Strategic Plan Objectives 7.D | Projects2 |
Funding$436,815 |
Percent of Total ASD Funding<1% |
2010 IACC Strategic Plan ObjectivesNew! | Projects2 |
Funding$330,662 |
Percent of Total ASD Funding<1% |
2010 IACC Strategic Plan ObjectivesNew! | Projects0 |
Funding$0 |
Percent of Total ASD Funding0% |
2010 IACC Strategic Plan ObjectivesNew! | Projects0 |
Funding$0 |
Percent of Total ASD Funding0% |
2010 IACC Strategic Plan ObjectivesNew! | Projects2 |
Funding$1,932,996 |
Percent of Total ASD Funding1% |
2010 IACC Strategic Plan ObjectivesNew! | Projects15 |
Funding$6,715,815 |
Percent of Total ASD Funding2% |
2010 IACC Strategic Plan ObjectivesNew! | Projects11 |
Funding$494,449 |
Percent of Total ASD Funding<1% |
2010 IACC Strategic Plan ObjectivesNew! | Projects7 |
Funding$2,527,472 |
Percent of Total ASD Funding1% |
2010 IACC Strategic Plan ObjectivesNew! | Projects2 |
Funding$699,304 |
Percent of Total ASD Funding<1% |
2010 IACC Strategic Plan ObjectivesNew! | Projects0 |
Funding$0 |
Percent of Total ASD Funding0% |
2010 IACC Strategic Plan Objectives | Projects2 |
Funding$1,000,000 |
Percent of Total ASD Funding<1% |
2010 IACC Strategic Plan ObjectivesTotal Funding for Question 7 | Projects46 |
Funding$15,809,755 |
Percent of Total ASD Funding5% |
The percentages noted in parentheses in the "Projects" and "Funding" columns indicate the fraction of all projects or funding within that specific question, whereas the percentage in the "Percent of Total ASD Funding" column indicates the percent of the entire ASD research funding portfolio for 2009.
Other – Not specific to IACC Strategic Plan questions
IACC Strategic Plan Objectives | Projects | Funding | Percent of Total ASD Funding |
---|---|---|---|
2010 IACC Strategic Plan ObjectivesOther | Projects31 |
Funding$17,126,749 (100%) |
Percent of Total ASD Funding5% |
Grand Total
IACC Strategic Plan Objectives | Projects | Funding | Percent of Total ASD Funding |
---|---|---|---|
2010 IACC Strategic Plan ObjectivesTotal ASD Funding for 2009 | Projects995 |
Funding$314,385,374 |
Percent of Total ASD Funding100% |
The percentages noted in parentheses in the "Projects" and "Funding" columns indicate the fraction of all projects or funding within that specific question, whereas the percentage in the "Percent of Total ASD Funding" column indicates the percent of the entire ASD research funding portfolio for 2009.
References
1 Budget recommendations were formulated by scientific and program experts in the field and provide an estimate of what it would cost to conduct each project. The IACC provides these budget recommendations as guidance to Federal agencies and partner organizations as to the potential cost of conducting the recommended research. The IACC's role in research is advisory. The committee does not have its own research budget to conduct or support research.
2 When Question 7 was added to the IACC Strategic Plan in 2010, several ongoing projects were moved from other questions' objectives for a better fit within Question 7.